Mammoet returns to Bruce Power to assist nuclear power plant upgrades

Mammoet is returning to Bruce Power in Ontario to continue its work in the Major Component Replacement (MCR) project that will extend the life of the nuclear power plants.

Construction of the MCR project began in 2020 and includes replacement of major components within six reactor units across the Bruce A and B stations.

When in operation, these stations power more than 30 per cent of the province and produce cancer-fighting medical isotopes.

Mammoet supported the steam generator exchanges at Unit 3 of Bruce A in 2024. It will now return to the station to perform a similar scope for Unit 4.

“Mammoet continues to help us safely execute our MCR projects that will extend the life of Bruce Power for decades to come,” said Rob Hoare, Vice President of MCR Execution. “From its specialist equipment that has made these efficient exchanges fast, efficient and safe, to its engineering support Mammoet have been a critical partner for the success of the project.”

This project is being carried out for Bruce Power and the Steam Generator Replacement Team (SGRT) — an equal joint venture between Aecon and SGT — a partnership of Framatome and Unite Engineers and Constructors.

More news from Mammoet

Mammoet is providing SGRT with lifting, transport and jack-and-slide services to relocate two steam drums and exchange eight steam generators at Unit 4.

This process is expected to take about six months and will once again utilize Mammoet’s 1,600-tonne capacity PTC-35 ring crane and jack-and-slide equipment.

Mammoet Self-Propelled Modular Transporters (SPMTs) will be on site to move the end-of-life steam generators into long-term storage.

By combining power with portability, the PTC ring crane is playing a key role in the safe and efficient exchanges of the steam generators.

“A crawler crane of similar capacity would require a big counterweight, which would need to be continually picked up and set back down,” said Gord Gilchrist, Business Development Director at Mammoet. “Not only does this add risk, but it takes up more time and room. The other advantage of the PTC is that it can stand tall in extreme weather using a storm anchor. 

“This is key because the site can see very heavy wind conditions. If you were to use a crawler, the high winds could mean having to down boom”.